Submittals in Construction: A Complete Guide to the Process, the Log and the Review
Last updated: November 2026
Construction submittals are the shop drawings, product data, samples and supporting documents a contractor sends to the design team to show that the materials and equipment it plans to buy and install meet the contract documents. The architect or engineer reviews each one, stamps it, and sends it back before anything is ordered, fabricated or built.
That sounds like paperwork, and on a lot of jobs it gets treated like paperwork. It is actually the gate between design and procurement, and procurement is where schedules are won or lost right now. At a September 2026 webinar on materials costs, a Skanska supply chain vice president said structural steel prices had climbed 25% over the past year while lead times had more than doubled to 55 weeks, as reported by Construction Dive. When a single package can take more than a year to arrive, a steel shop drawing that sits in a reviewer's inbox for three extra weeks, or comes back "revise and resubmit" twice, is no longer an admin problem. It is a schedule problem, a cash flow problem, and eventually a claim.
This guide covers what submittals in construction are, the main types, who does what, the submittal process from start to closeout, how to build a construction submittal log that people actually use, what review stamps mean, and the mistakes that cause most delays. It is written for general contractors, owners and developers, project managers and controllers who want the submittal process to run on time instead of on memory.
What Is a Submittal in Construction?
A submittal is any document or physical item the contractor is required to send to the design team so they can confirm that a specific product, system or assembly complies with the design intent. The project specifications list which submittals are required for each section of work, what each package must contain, and how many days the reviewer has to respond.
Submittals exist because drawings and specifications describe a building in performance terms and in general dimensions, while the people who actually fabricate and install it work with specific products, specific model numbers and specific connection details. The submittal is where those two worlds meet. The architect gets to confirm that the curtain wall system the glazing sub picked will meet the specified thermal and structural performance. The mechanical engineer gets to confirm that the rooftop units fit the structural openings and the electrical capacity. The owner gets one last chance to see what is actually going into the building before money is committed.
It helps to be clear about what a submittal is not. In most standard contract forms, approved submittals are not contract documents. They show how the contractor intends to meet the contract documents; they do not change them. If a submittal quietly deviates from the specs and the reviewer misses it, the approval generally does not relieve the contractor of the obligation to meet the original requirement unless the deviation was specifically called out and accepted. Every contract is different, so read the general conditions and Division 01 of your project manual rather than relying on a rule of thumb, and involve your legal adviser for anything that looks like a real dispute.
Types of Construction Submittals
Most construction submittals fall into a handful of categories. Specifications often group them as "action submittals" (the reviewer must respond with a decision) and "informational submittals" (the reviewer receives them for the record but does not approve them).
Submittal type | What it shows | Typically prepared by | Typical reviewer |
|---|---|---|---|
Shop drawings | Fabrication and installation details specific to this job | Subcontractor, fabricator or supplier | Architect and relevant engineer |
Product data | Manufacturer cut sheets, performance data, model numbers | Supplier or subcontractor | Architect or engineer |
Samples | Physical pieces of finishes, colours and materials | Supplier | Architect, sometimes the owner |
Mock-ups | Full-size assemblies built on or near site | Subcontractor | Architect, owner, sometimes a testing agency |
Test reports and certificates | Proof that materials meet a standard or test | Manufacturer or testing lab | Engineer or architect (often informational) |
Delegated design calculations | Engineering by a specialty engineer hired by the contractor | Specialty engineer | Engineer of record |
O&M manuals and warranties | Operating, maintenance and warranty information for turnover | Subcontractor and supplier | Architect and owner at closeout |
A few of these deserve a one-line definition because they get confused on site:
- Shop drawings: Drawings prepared by the contractor, a sub or a fabricator that show exactly how a component will be made and installed on this particular project, such as steel connection details, duct layouts or millwork elevations.
- Product data: Standard manufacturer information (cut sheets, catalogue pages, performance charts) marked up to show which model, size and option the contractor is proposing.
- Samples: Physical examples that set the standard the finished work will be judged against, such as a brick, a paint drawdown or a carpet tile.
- Mock-ups: Full-size built sections of an assembly, like a wall panel with window, flashing and cladding, used to confirm appearance and performance before the real work starts.
- Closeout submittals: O&M manuals, warranties, attic stock lists and as-built information delivered at the end of the job, usually tracked in the same submittal log.
Who Is Involved in the Submittal Process?
The submittal process runs through at least four parties, and most delays happen at the hand-offs between them.
- Subcontractors and suppliers: They prepare most shop drawing submittals and product data, because they are the ones who know the exact product, dimensions and fabrication method.
- General contractor: The GC coordinates every package, checks it against the contract documents and against the work of other trades, stamps it, and sends it to the design team. The GC is accountable for the schedule and for what gets installed.
- Architect and engineers: The design team reviews submittals for general conformance with the design intent and returns them with a review stamp and comments.
- Owner or owner's representative: Often reviews samples, colours, mock-ups and anything that changes cost, schedule or operations, and receives closeout submittals at turnover.
Collecting the right paperwork from subcontractors before they start is related but separate. Insurance certificates, licences and bonds are compliance documents rather than submittals, and they belong in their own tracking process; our guide to essential subcontractor compliance documents covers that list.
Where Submittal Requirements Live: Spec Section 01 33 00
On most North American projects that follow the Construction Specifications Institute's MasterFormat numbering, the general rules for construction submittals sit in Division 01, Section 01 33 00, Submittal Procedures. That section typically sets out:
- How submittals are transmitted (paper, email, a project platform)
- How packages must be numbered and identified
- The review period the design team is allowed, and whether it restarts on resubmission
- What the contractor must review and stamp before sending
- How deviations from the specs must be flagged
- The number of copies, sample sets, or electronic formats required
The technical sections (for example Section 05 12 00 for structural steel framing or Section 08 44 13 for glazed curtain walls) then list the specific submittals needed for that scope in a "Submittals" article, usually in Part 1 of the section. Building your construction submittal log starts with reading every one of those articles and turning each required item into a line.
The Submittal Process, Step by Step
Every project and every specification is a little different, but the submittal process on a typical commercial job follows the same sequence.
- Build the register from the specs. Go through Section 01 33 00 and every technical section and list each required submittal. This becomes the first version of your construction submittal log.
- Set the submittal schedule. For each item, work backward from the date the material must be on site: installation date, minus delivery lead time, minus fabrication time, minus review time (including one resubmission), equals the date the submittal must leave your office.
- Request packages from subs and suppliers. Send each responsible party the spec references, the required contents, and the date you need it. Make the due date earlier than the date it has to go to the architect so you have time to review.
- Review and stamp as the GC. Check the package against the specs, drawings, field conditions and the work of other trades. Mark up conflicts, send back incomplete packages, and stamp only what you have actually reviewed.
- Transmit to the design team. Send the package for submittal review with a transmittal that lists the submittal number, spec section, revision number and any deviations you are asking the reviewer to accept.
- Design review and stamp. The architect and relevant engineers review for general conformance and return the package with one of the standard review actions and comments.
- Distribute the result. Send the reviewed package back to the sub or supplier, update the log, and release the order or fabrication if the stamp allows it.
- Resubmit if needed. For "revise and resubmit" or "rejected" outcomes, the sub corrects the package, the GC re-reviews it, and it goes back through steps 4 to 7 with a new revision number.
- Close out. At the end of the job, collect O&M manuals, warranties and as-built information, confirm every line in the log is closed, and hand the record to the owner.
Two habits make the submittal process far more predictable. First, keep one numbering convention for the whole project, usually spec section plus a sequence number plus a revision suffix (for example 05 12 00-003 Rev 1). Second, never let a resubmission go out without the reviewer's previous comments answered one by one; unanswered comments are the most common reason a second review turns into a third.
How to Build a Construction Submittal Log

The construction submittal log (also called a submittal register) is the single list of every required submittal on the project and where each one stands. A good log answers three questions at a glance: what is late, who has the ball, and which purchases are waiting on it.
These are the columns that earn their place:
Column | What goes in it |
|---|---|
Submittal number | Spec section plus sequence, for example 08 44 13-002 |
Revision | 0 for the first submission, then 1, 2 and so on |
Spec section and description | The section and a plain-language name, for example "Curtain wall shop drawings" |
Type | Shop drawing, product data, sample, mock-up, certificate, closeout |
Responsible sub or supplier | Company and contact preparing the package |
Required on-site date | When the material must arrive to hold the schedule |
Lead time | Fabrication plus delivery, confirmed with the supplier |
Date due from sub | Internal deadline for the package |
Date sent to reviewer | When the GC transmitted it |
Review period and date due back | Per Section 01 33 00 |
Date returned and review action | Actual return date and the stamp received |
Ball in court | Who must act next: sub, GC, architect, engineer, owner |
Linked commitment | The subcontract or purchase order the approval releases |
Status and notes | Open, closed, overdue, and anything the next person needs to know |
Here is what a few rows look like on a mid-size commercial job:
No. | Rev | Description | Ball in court | Due back | Action | Linked commitment |
|---|---|---|---|---|---|---|
05 12 00-001 | 1 | Structural steel shop drawings, Level 2 | Architect / structural engineer | Oct 14 | Pending | Steel subcontract |
08 44 13-002 | 0 | Curtain wall product data | Glazing sub | Oct 03 | Revise and resubmit | Glazing subcontract |
23 73 13-001 | 0 | Air-handling units product data | GC review | Sep 30 | Not yet sent | Mechanical PO |
09 91 23-004 | 0 | Interior paint colour samples | Owner | Oct 21 | Pending | Painting subcontract |
Two columns in that list are the ones most logs are missing. "Ball in court" turns a static list into a to-do list for the weekly meeting. "Linked commitment" connects the submittal to money, which matters more than most teams realise, and we come back to it below.
A spreadsheet is fine for a small job with a few dozen submittals. Once you are running several projects with hundreds of lines each, the problem stops being the template and starts being the fact that the log, the email trail and the purchasing records all live in different places and drift apart.
What Submittal Review Stamps Mean
When the design team returns a submittal, it carries a review stamp. Wording varies by firm and by specification, but most stamps come down to four outcomes.
- Approved (or "No exceptions taken"): The package conforms to the design intent as submitted. The contractor can release fabrication or purchasing, still subject to the contract documents.
- Approved as noted (or "Make corrections noted"): The package conforms if the reviewer's comments are incorporated. Work can usually proceed with the corrections, and some specs require a corrected copy for the record.
- Revise and resubmit: The package does not conform or is incomplete. Do not release fabrication or purchasing. Correct it and resubmit as the next revision.
- Rejected (or "Not accepted"): The product or approach does not meet the requirements. Select a compliant product or method and submit a new package.
Some firms add "Reviewed, for record only" or "Received for information" for informational submittals such as certificates and test reports. Whatever the wording, record the exact stamp in the construction submittal log and treat anything other than a clear approval as a hold on the related purchase until someone on your team reads the comments.
Submittal Timelines and How to Keep Them From Delaying Procurement
The review period is set by the contract, most often in Section 01 33 00, and is usually expressed as a number of working or calendar days from receipt. Read it carefully, because many specifications restart the clock on every resubmission and allow extra time for packages that need consultant review. A package that needs two rounds can easily consume double the time on the schedule, before a single piece of material is ordered.
With long-lead items now measured in many months, the submittal schedule is really a procurement schedule. A few practices keep it honest:
- Front-load long-lead items: Get structural steel, switchgear, elevators, curtain wall and major mechanical equipment submittals moving first, even if other packages have to wait.
- Plan for one resubmission: Build at least one revise-and-resubmit cycle into the schedule for complex shop drawing submittals. If it comes back approved the first time, you have float.
- Agree on review order with the design team: Share the submittal schedule at the start of the job so the architect and engineers can staff for the peaks instead of discovering them.
- Split large packages sensibly: Break a building-wide package into areas or levels if that gets critical fabrication started sooner, but do not split in ways that stop the reviewer from seeing how the system works as a whole.
- Track ball in court weekly: Review every open line in the weekly meeting and name the person who owns the next step.
There is also a financial side to submittal review that project teams rarely talk about. An approved submittal is often the moment a commitment becomes real: the steel fabricator starts buying material, the equipment supplier releases the order, and the committed cost on that job firms up. Premier Construction Software's team draws this line plainly when it compares its construction ERP for general contractors with project-management-only tools: those tools do "just management," while Premier Construction Software runs financials and project management together. For submittals, the difference is concrete. A management-only tool tracks the document; a connected platform can also show what that approval releases in committed cost. That is why we recommend a "linked commitment" column even in a spreadsheet log. When a steel submittal comes back "revise and resubmit", the controller should see the same risk the project manager sees.
Premier Construction Software is built as an all-in-one construction ERP for both construction managers and controllers. Submittal management is one of the places where those two roles need the same picture. The PM needs to know whether fabrication can start. The controller needs to know whether a large commitment is about to hit, or is about to slip into next month. A construction submittal log that only the project team can read leaves the finance side forecasting blind.
Submittals vs RFIs: What Is the Difference?
Submittals and RFIs travel the same route between contractor and design team, so they get confused. The difference is direction and purpose.
Submittal | RFI | |
|---|---|---|
Purpose | Show that a proposed product or method meets the contract documents | Ask a question about the contract documents |
Who starts it | Contractor, usually prepared by a sub or supplier | Contractor, often raised by the field or a sub |
Required by | The specifications (listed in each technical section) | Raised as needed when information is missing or conflicting |
Typical output | A review stamp and comments | A written answer, sometimes a revised drawing |
Timing | Scheduled in advance around procurement | Unplanned, whenever a gap is found |
A simple test: if you are asking the design team to confirm something you are proposing, it is a submittal. If you are asking the design team to tell you something the documents do not make clear, it is an RFI. Do not bury questions inside construction submittals, and do not use RFIs to sneak in a product substitution; both habits leave a gap in the record when someone later asks why a decision was made.
Common Submittal Mistakes and How to Avoid Them
Most late submittals in construction trace back to a short list of repeat mistakes.
- Missing spec references: Packages that do not say which spec section and paragraph they respond to force the reviewer to hunt, and hunting takes days. Put the section number on every page of the transmittal.
- Pass-through stamping: Forwarding a sub's package without a real GC review guarantees avoidable rejections and, as the AIA guidance above makes clear, does not meet the contractor's obligation.
- Incomplete packages: A curtain wall submittal without anchor calculations, or a product data sheet with no options marked, comes back "revise and resubmit" by default. Check the spec's content list before you send anything.
- Undisclosed deviations: Substitutions or deviations that are not clearly flagged are one of the biggest sources of dispute later. Call them out on the transmittal and in a cover letter, and ask for an explicit decision.
- Late starts on long-lead items: Waiting for every drawing to be final before starting shop drawing submittals means your longest-lead items start last. Sequence the log by lead time, not by spec section.
- No version control: When revision 0, revision 1 and a marked-up email attachment all float around, somebody fabricates from the wrong one. Keep one current version, one numbering scheme, and archive superseded revisions clearly.
- Installing before approval: Work installed ahead of an approved submittal is installed at the contractor's risk. If it does not match what the reviewer eventually accepts, removal and rework usually land on the contractor.
- Forgetting closeout: O&M manuals and warranties left to the last month hold up substantial completion paperwork and retainage. Log them from day one, with the same due dates and ball-in-court tracking as everything else.
Managing Submittals in Construction Software
Spreadsheets and shared inboxes can carry a small project, but submittal management across a portfolio needs a system that keeps the log, the documents, the reviewers and the history in one place. When you evaluate submittal software, look for:
- Guest access for outside reviewers: Architects, engineers, subs and suppliers should be able to submit, review and respond without buying a seat.
- Configurable approval workflows: Multi-level approvals that route a package from the sub to the GC to the design team and back, with a clear record of who acted and when.
- Version history: Every revision retained, with the current one obvious.
- Mobile access: Field teams checking the construction submittal log on site to confirm a product was approved before it gets installed.
- A link to cost: Approved submittals that connect to the subcontract or purchase order they release, so committed cost and forecasts reflect reality.
The last point is where a construction ERP and a stand-alone document tool part ways. Premier Construction Software manages RFIs, submittals, tasks, punch lists, inspections, meetings, daily job logs and approvals within its construction software for project managers, with free guest access for subcontractors, suppliers, architects and engineers and configurable workflows with multi-level approvals. Because that sits in the same platform as real-time job costing and commitments, the submittal a PM is chasing and the purchase order a controller is forecasting are part of the same record for general contractors and owners who want one view of the job.
Frequently Asked Questions
Who is responsible for submittals?
The general contractor coordinates construction submittals and is accountable for them. Subcontractors and suppliers usually prepare the packages, the GC reviews and stamps them, and the architect or engineer reviews them for conformance with the design intent. The owner may review samples, colours and anything that affects cost or operations.
What happens if work is installed before a submittal is approved?
The contractor generally carries the risk. If the installed work does not match what the design team later accepts, the contractor can be required to remove and replace it at its own cost. Check your contract's general conditions and Section 01 33 00 for the exact language on your project.
Are submittals part of the contract documents?
Generally no. Under most standard contract forms, submittals demonstrate how the contractor will meet the contract documents rather than becoming part of them, and an approval does not normally authorise a change unless a deviation was specifically identified and accepted. Contracts vary, so confirm with your own documents and legal adviser.
How many times can a submittal be resubmitted?
There is usually no fixed limit on resubmissions in the submittal process. Some owner and architect agreements cap the number of reviews included in the design fee, and additional reviews can become billable to the owner, who may then look to the contractor. Plan for one resubmission on complex packages and aim for none.
How long does submittal review take?
The review period is set in the contract, most often in Section 01 33 00, and is usually stated in working or calendar days from receipt. Complex packages that need consultant input often get a longer window, and many specs restart the clock on each resubmission.
What is the difference between a submittal log and a submittal schedule?
The construction submittal log records every required submittal and its current status. The submittal schedule sets the dates each package must be submitted and returned, based on when the material has to be on site. In practice, most teams keep both in the same register.
Key Takeaways
- Submittals are the gate to procurement: With long-lead materials measured in many months, the submittal schedule is effectively your procurement schedule.
- The GC stamp means real review: Pass-through stamping invites rejections and does not meet the contractor's obligation under common contract forms.
- Build the log from the specs: Section 01 33 00 and each technical section's "Submittals" article define every line in your construction submittal log.
- Track ball in court and linked commitments: Those two columns turn a static register into a weekly action list and connect approvals to cost.
- Flag deviations and control versions: Undisclosed substitutions and mixed-up revisions cause most late-stage disputes and rework.
- Connect submittals to financials: When approvals and commitments live in one system, project managers and controllers work from the same picture.
Conclusion
Construction submittals will never be the most exciting part of a project, but they decide whether material shows up on time and whether the money committed to it is visible when it matters. Start with a register built from the specifications, schedule every package from the required on-site date backward, review honestly before you stamp, and keep ball in court and linked commitments visible every week. If your team is managing construction submittals, RFIs and approvals across several jobs and wants that work tied directly to job costing and financials, Premier Construction Software gives general contractors, owners and developers one cloud construction ERP where project managers and controllers see the same submittal status, the same commitments and the same forecast.